Greendale
Stadium
Student’s
Name
Instructor
Institution
Date
Part
A
Table
1: Work Breakdown Structure
No.
|
Task
|
Duration (days)
|
Start
|
Finish
|
Predecessors
|
1
|
Stadium site clearance
|
60
|
September 22, 2012
|
December 20, 2012
|
|
2
|
Demolishing building
|
30
|
December 28, 2012
|
February 1, 2013
|
1
|
3
|
Site setup
|
60
|
February 8, 2013
|
May 3, 3013
|
2
|
4
|
Drive support piling
|
120
|
December 28, 2012
|
May 13, 2013
|
1
|
5
|
Pouring lower concrete bowl
|
110
|
June 14, 2013
|
November 15, 2013
|
2
|
6
|
Pouring main course
|
110
|
November 29, 2013
|
May 2, 2014
|
5
|
7
|
Playing field installation
|
80
|
November 29, 2013
|
March 21, 2014
|
2
|
8
|
Construction of upper steel bowl
|
110
|
November 29, 2013
|
May 3, 2014
|
6
|
9
|
Seat installation
|
120
|
May 16, 2014
|
November 15
|
6, 8
|
10
|
Build luxury boxes
|
70
|
May 16, 2014
|
October 25, 2014
|
6
|
11
|
Jumbotron installation
|
50
|
May 16, 2014
|
June 18, 2014
|
8
|
12
|
Stadium infrastructure
|
130
|
May 16, 2014
|
November 5, 2014
|
9
|
13
|
Steel canopy construction
|
80
|
November 28, 2014
|
March 20, 2015
|
13
|
14
|
Lighting
|
40
|
March 13, 2015
|
May 10, 2015
|
4
|
15
|
Roof support construction
|
50
|
November 29, 2013
|
March 12, 2014
|
15
|
16
|
Roof construction
|
160
|
April 4, 2014
|
November 16, 2014
|
15
|
17
|
Roof tracks construction
|
100
|
April 4, 2014
|
August 20, 2014
|
17
|
18
|
Installation of roof
|
100
|
December 12, 2014
|
April 15, 2015
|
7, 12, 18
|
19
|
Inspection
|
20
|
April 4, 2015
|
May 17, 2015
|
18
|
20
|
Report preparation
|
30
|
May 1, 2015
|
June 12, 2015
|
19
|
Part
B
The critical path refers to the
order a network of activities in a project. It is a sequential series of
activities which shows the longest time the completion will take. The longest
duration the Greendale stadium would take to complete is 2 years and 8 months.
The project has also provided time allowances to accommodate for delays various
tasks may have. The time allowance for each project is known as slack. Float
prevents the delay in the completion of the whole project. The total slack for
the Greendale project is 8 months. Every activity has a slack to accommodate
for uncertainties the project may experience (Sears, 2015). Roof construction,
pouring the lower concrete bowl, seat installation, site clearance, and stadium
infrastructure are the activities that have the largest slack.
The activities that have been
allocated smallest float in the project are the ones that influence the
completion date for Greendale Stadium. Uncertainties in the course of project
implementation are limited, but they can be predicted and assessed early enough
to facilitate their prevention (Sears, 2015). Uncertainties cause unplanned
delays. In Greendale Stadium project, the top three tasks that influence the
complete date are the setup of the construction site, playing field
installation, and the construction of steel canopy. These three activities
determine the duration of the tasks with the largest slack by influencing the
start and completion times.
Planning is an important activity
that I would incorporate into the project since it affects the how and when
other activities are conducted. Planning involves activities such as
forecasting and resource allocation according to the needs of each task. The
tasks with poor resource allocation may experience delays in their completion
due to inefficiencies. Adequate resource allocation reduces the chances of
errors and thus, helps in preventing repeating tasks. After the inspection,
there should be another activity to address unwanted outcomes in the project.
References
Sears, S. K.
(2015). Construction Project Management Sixth Edition Red Vector
Bundle: ; Clough. Hoboken, NJ: Wiley.
No comments:
Post a Comment