Saturday, September 2, 2017

Greendale project









Greendale Stadium
Student’s Name
Instructor
Institution
Date




Part A
Table 1: Work Breakdown Structure
No.
Task
Duration (days)
Start
Finish
Predecessors
1
Stadium site clearance
60
September 22, 2012
December 20, 2012

2
Demolishing building
30
December 28, 2012
February 1, 2013
1
3
Site setup
60
February 8, 2013
May 3, 3013
2
4
Drive support piling
120
December 28, 2012
May 13, 2013
1
5
Pouring lower concrete bowl
110
June 14, 2013
November 15, 2013
2
6
Pouring main course
110
November 29, 2013
May 2, 2014
5
7
Playing field installation
80
November 29, 2013
March 21, 2014
2
8
Construction of upper steel bowl
110
November 29, 2013
May 3, 2014
6
9
Seat installation
120
May 16, 2014
November 15
6, 8
10
Build luxury boxes
70
May 16, 2014
October 25, 2014
6
11
Jumbotron installation
50
May 16, 2014
June 18, 2014
8
12
Stadium infrastructure
130
May 16, 2014
November 5, 2014
9
13
Steel canopy construction
80
November 28, 2014
March 20, 2015
13
14
Lighting
40
March 13, 2015
May 10, 2015
4
15
Roof support construction
50
November 29, 2013
March 12, 2014
15
16
Roof construction
160
April 4, 2014
November 16, 2014
15
17
Roof tracks construction
100
April 4, 2014
August 20, 2014
17
18
Installation of roof
100
December 12, 2014
April 15, 2015
7, 12, 18
19
Inspection
20
April 4, 2015
May 17, 2015
18
20
Report preparation
30
May 1, 2015
June 12, 2015
19


Part B
The critical path refers to the order a network of activities in a project. It is a sequential series of activities which shows the longest time the completion will take. The longest duration the Greendale stadium would take to complete is 2 years and 8 months. The project has also provided time allowances to accommodate for delays various tasks may have. The time allowance for each project is known as slack. Float prevents the delay in the completion of the whole project. The total slack for the Greendale project is 8 months. Every activity has a slack to accommodate for uncertainties the project may experience (Sears, 2015). Roof construction, pouring the lower concrete bowl, seat installation, site clearance, and stadium infrastructure are the activities that have the largest slack.
The activities that have been allocated smallest float in the project are the ones that influence the completion date for Greendale Stadium. Uncertainties in the course of project implementation are limited, but they can be predicted and assessed early enough to facilitate their prevention (Sears, 2015). Uncertainties cause unplanned delays. In Greendale Stadium project, the top three tasks that influence the complete date are the setup of the construction site, playing field installation, and the construction of steel canopy. These three activities determine the duration of the tasks with the largest slack by influencing the start and completion times.
Planning is an important activity that I would incorporate into the project since it affects the how and when other activities are conducted. Planning involves activities such as forecasting and resource allocation according to the needs of each task. The tasks with poor resource allocation may experience delays in their completion due to inefficiencies. Adequate resource allocation reduces the chances of errors and thus, helps in preventing repeating tasks. After the inspection, there should be another activity to address unwanted outcomes in the project.



References
Sears, S. K. (2015). Construction Project Management Sixth Edition Red Vector Bundle: ; Clough. Hoboken, NJ: Wiley.

No comments:

Post a Comment